Ask Question
24 February, 03:35

At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration effort, but they cannot integrate every Iteration and meet the planned scope. What should the Scrum Master suggest?

+1
Answers (1)
  1. 24 February, 07:02
    0
    The scrum master can suggest that:

    Postpone the work on system integration for a while until the train is in sustain and enhance the section of road map of implementation

    Explanation:

    System Demo:

    It is such a software that is used to measure the progress of Agile Release Train.

    As the teams didn't expect that the integration of system will be a difficult task and they ultimately failed to accomplish the goal of integration so that scrum master asked them to stop working on the system integration until the Agile Release Train's sustainability and to improve and optimize the implementation of road map.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “At the System Demo, each team demonstrates their own work but the system is not integrated. They say they underestimated the integration ...” in 📙 Physics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers