Ask Question
11 November, 20:39

Which of the following is NOT part of the project controlling?

a. shifting resources to where they are needed most

b. sequencing and allotting time to all project activities

c. close monitoring of resources, costs, quality, and budgets

d. using a feedback loop to revise the project plan

+2
Answers (1)
  1. 11 November, 22:36
    0
    b. sequencing and allotting time to all project activities

    Explanation:

    ' Project Controls are data collection, data management and predictive methods used to forecast, interpret and proactively control the time and cost results of a project or program; by communicating information in ways that enable effective management and decision-making.

    So, a, c and d are statements are a part of project controlling but b that is

    sequencing and allotting time to all project activities is not a part of project controlling.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following is NOT part of the project controlling? a. shifting resources to where they are needed most b. sequencing and ...” in 📙 Physics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers