In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

a) true

b) false

+2
Answers (1)
  1. 27 July, 01:10
    0
    The correct answer is True.

    Explanation:

    This type of practice is common to evaluate the conditions in the most pessimistic scenario. The 99% accuracy is fundamental to set the most pessimistic duration of a project, because it guarantees to have a high confidence interval to ensure that the actual duration will be equal or less than the most pessimistic duration.

    Have a nice day!
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% ...” in 📙 Physics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers