Ask Question
10 September, 12:09

A distribution system comprises 2 central distribution centers (which are both replenished from a single plant), 8 regional warehouses, and 56 stores. The replenishment lead times are as follows: plant (2 weeks), DC (1 week), regional warehouse (1 week), store (1 week). What is the minimum planning horizon?

+1
Answers (1)
  1. 10 September, 14:30
    0
    5 weeks.

    Explanation:

    The replenishment lead times are 2 weeks for the plant, 1 week for the DC,! week for the regional warehouse and 1 week for the store.

    The planning horizon is the amount of time that will be required by an organization when the organization is preparing for a strategic plan.

    So the minimum planning horizon is 5 weeks.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A distribution system comprises 2 central distribution centers (which are both replenished from a single plant), 8 regional warehouses, and ...” in 📙 Social Studies if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers