The project manager should schedule the meeting immediately following the delivery of the final report rather than waiting for a time when the customer is in a position to really determine whether the project met expectations and achieved the anticipated benefits.

+1
Answers (1)
  1. 16 April, 21:54
    0
    False

    Explanation:

    This basically is the closing phase of the project, usally in this phase the deliverable meaing the product has already been delivered to the customer and the customer has accepted that the product or service has met expectations. By the time the project manager is delivering the final report the project is virtually closed, if the project manager is scheduling a meeting following the delivery of the final report, it has no impact.

    When the final report is delivered all other project management documents are being submitted including lessons learned so there is no basis for a meeting.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The project manager should schedule the meeting immediately following the delivery of the final report rather than waiting for a time when ...” in 📙 Social Studies if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers