One common mistake made early in the risk identification process is

a. not all possibilities are considered

b. participants are over-optimistic

c. participants are over-pessimistic

d. focus on objectives and not on the events that could produce consequences.

e. too much attention is given to past events

+5
Answers (1)
  1. 11 April, 20:52
    0
    The risk identification process identificates the risks that could potentially prevent the program, enterprise, or investment from achieving its objectives.

    One common mistake made early in the risk identification process is that it is f ocusing on objectives and not on the events that could produce consequences.

    Correct answer: D
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “One common mistake made early in the risk identification process is a. not all possibilities are considered b. participants are ...” in 📙 Social Studies if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.