In January, Dieker Company requisitions raw materials for production as follows: Job 1 $970, Job 2 $1,520, Job 3 $810, and general factory use $660. During January, time tickets show that the factory labor of $7,600 was used as follows: Job 1 $2,390, Job 2 $1,730, Job 3 $1,560, and general factory use $1,920.

Prepare the job cost sheets for each of the three jobs.

+1
Answers (1)
  1. 13 April, 02:42
    0
    Dieker Company

    Job Cost Sheet of

    Job1 Job2 Job3

    Materials $970 $ 1520 $ 810

    Factory Labor $2390 $ 1730 $1560

    General Factory

    Indirect material $ 660 $ 660 $ 660

    Indirect labor $ 1920 $ 1920 $ 1920

    Total $ 5940 $5830 $ 4950

    Cost of Job 1

    Materials $ 970

    Factory Labor $ 2390

    G. Factory $ 2580

    Total $ 5940

    Cost of Job 2

    Materials $ 1520

    Factory Labor $ 1730

    G. Factory $ 2580

    Total $ 5830

    Cost of Job 3

    Materials $ 810

    Factory Labor $ 1560

    G. Factory $ 2580

    Total $ 4950
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In January, Dieker Company requisitions raw materials for production as follows: Job 1 $970, Job 2 $1,520, Job 3 $810, and general factory ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.