Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as

+2
Answers (2)
  1. 20 July, 09:42
    0
    accepted

    Explanation:

    An accepted completion date refers to an agreed completion date. In this case, both parties agree that the delivery of goods, services, report, etc., must be completed by a certain date.

    In this case, Scott and top managers got together and discussed a completion date that was accepted by both parties (upper management and Scott). They also agreed that Scott might get some extra days to deliver the final project if that meant that the targeted costs will be met.
  2. 20 July, 11:49
    0
    On Time Delivery.

    Explanation:

    On time deliveries are not specific. They are dates that are spaced out and grouped as early (X) and late or late (Y). Delivery or completion date are set between 5 days early to 0 day, due date.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.