Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as
+2
Answers (2)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.