An advertising agency is estimating costs for advertising a music festival. The job will require 230 direct labor hours at a cost of $56 per hour. Overhead costs are applied at a rate of $68 per direct labor hour. What is the total estimated cost for this job?

+3
Answers (1)
  1. 5 July, 04:24
    0
    The total estimated cost for this job is $28,520

    Explanation:

    In order to calculate the total estimated cost for this job we would have to make the following calculation:

    Total estimated cost=Total direct labor cost+Actual overhead applied cost

    Total direct labor cost=total required labour hours*cost per direct labour hour

    hence, Total direct labor cost=230*$56

    Total direct labor cost=$12,880

    Actual overhead applied cost=total required labour hours*Appliead overhead cost

    hence, Actual overhead applied cost=230*$68

    Actual overhead applied cost=$15,640

    Therefore, Total estimated cost=$12,880+$15,640

    Total estimated cost=$28,520

    The total estimated cost for this job is $28,520
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “An advertising agency is estimating costs for advertising a music festival. The job will require 230 direct labor hours at a cost of $56 ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.