Copy Center pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each employee hour worked. Materials are assigned to each job according to actual cost. Jobs are marked up 20% above cost to determine the selling price. If Job M-47 used $315 of materials and took 20 hours of labor to complete, what is the selling price of the job?

+3
Answers (1)
  1. 14 November, 17:07
    0
    The selling price is $1098

    Explanation:

    Labor $12 x hour

    Overhead $18 x hour

    Job M-47 took 20 hours, so it would be ($12+$18) * 20=$600 + $315 of materials = $915

    Total cost = $915 * 1.2 (the 20% mark up over cost) = $1098
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Copy Center pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers