What is the correct answer regarding short-run and long-run budgets? a. A short-run budget is generally less than a year in length and often tied to a particular project b. None of the answers are correct c. A long-run budget is generally one year in length and often tied to a particular department or division d. A long-run budget projects from two (2) to 10 years into the future

+5
Answers (1)
  1. 15 August, 01:42
    0
    Answer: Option A

    Explanation: In simple words, Short run budgets refers to the budgets which are made for a period of less than 12 months and long run budgets are made for a time period greater than one year.

    Short run budgets are prepared for some specific assets such as supplying a new customer for one year.

    Thus, from the above we can conclude that the correct option is A.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “What is the correct answer regarding short-run and long-run budgets? a. A short-run budget is generally less than a year in length and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers