In December, General Motors produced 7,500 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor hour during that month. 300 laborers were employed at the plant that month.

A) How many hours did the average laborer work that month?

B) If productivity can be increased to 0.12 vans per hour, how many hours would the average laborer work that month?

+5
Answers (1)
  1. 21 February, 21:35
    0
    Instructions are listed below.

    Explanation:

    Giving the following information:

    In December, General Motors produced 7,500 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor hour during that month. 300 laborers were employed at the plant that month.

    1) Total hours = 7,500/0.1 = 75,000 hours

    Hours per worker = 75,000/300 = 250 hours

    2) Total hours = 7,500/0.12 = 62,500 hours

    Hours per worker = 62,500/300 = 208 hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In December, General Motors produced 7,500 customized vans at its plant in Detroit. The labor productivity at this plant is known to have ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.