18 December, 22:05

Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at $10/hour) and that factory overhead would be $1,500,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,200,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate?

+1
Answers (1)
  1. 19 December, 01:05
    0
    The predetermined over head rate was 1,500,000/200,000=$7.5 of overhead charges per hour of labor
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.