Haft Construction Co. has consistently used the input method based on costs incurred to measure progress toward completion of the project. On January 10, Year 3, Haft began work on a $3 million construction contract. At the inception date, the estimated cost of construction was $2,250,000. The following data relate to the progress of the contract:
Gross profit recognized at 12/31/Yr 3
$ 300,000
Costs incurred 1/10/Yr 3 through 12/31/Yr 4
1,800,000
Estimated cost to complete at 12/31/Yr 4
600,000
In its income statement for the year ended December 31, Year 4, what amount of gross profit should Haft report?
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Haft Construction Co. has consistently used the input method based on costs incurred to measure progress toward completion of the project. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Home » Business » Haft Construction Co. has consistently used the input method based on costs incurred to measure progress toward completion of the project. On January 10, Year 3, Haft began work on a $3 million construction contract.