Why is it necessary to have a time-phased budget baseline? Select one: a. It allows proper resource allocation b. It reduces schedule slippage when scheduling multiproject resources c. It reduces fluctuations in cash flow during the project d. It shows how much work was accomplished for the money spent e. It is not necessary to have a time-phased budget baseline

+3
Answers (1)
  1. 31 March, 15:37
    0
    Answer:D. It shows how much work was accomplished for the money spent

    Explanation:

    Time phased budget is an approved plan of how much work should be accomplished at stated time on the money spent on a project
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Why is it necessary to have a time-phased budget baseline? Select one: a. It allows proper resource allocation b. It reduces schedule ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.