Ask Question
3 July, 17:59

XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000 while the actual overhead cost totaled $265,000. XYZ's estimated direct labor cost was $500,000 and the actual direct labor cost amounted to $510,000. For the current year, overhead was: Group of answer choices

+5
Answers (1)
  1. 3 July, 18:37
    0
    Allocated MOH = $255,000

    Explanation:

    Giving the following information:

    XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000; estimated direct labor cost was $500,000 and the actual direct labor cost amounted to $510,000.

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 250,000/500,000 = 0.5 per direct labor dollar

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 0.5*510,000 = $255,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000 ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers