A company had a choice between Project X and Project Y. The net present value of Project X is $1,000,000, and the net present value of Project Y is $750,000. The company chose Project X. What is the opportunity cost of that decision?

+5
Answers (1)
  1. 8 March, 11:47
    0
    The opportunity cost of that decision is - $250,000

    Explanation:

    For computing the opportunity cost, we have to use the formula of opportunity cost which is shown below:

    = Return of project which is not chosen - the return of a chosen project

    = $750,000 - $1,000,000

    = - $250,000

    Since in the question, it is given that the chosen project is X so we write the project X amount in the formula and the not chosen project of-course is Y.

    Hence, the opportunity cost of that decision is - $250,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A company had a choice between Project X and Project Y. The net present value of Project X is $1,000,000, and the net present value of ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.