Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided.
Days
Wait time 12
Inspection time 0.6
Process time 6
Move time 0.4
Queue time 8
Compute the manufacturing cycle efficiency (MCE).
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.