Ask Question
26 June, 16:44

Tower Company planned to produce 3,000 units of its single product, Titactium, during November. The standards for one unit of Titactium specify six pounds of materials at $0.30 per pound. Actual production in November was 3,100 units of Titactium. There was an unfavorable materials price variance of $380 and a favorable materials quantity variance of $120. Based on these variances, one could conclude that:

+2
Answers (1)
  1. 26 June, 20:32
    0
    The actual usage of materials was less than the standard allowed.

    Explanation:

    Based on these variances, one could conclude that the actual usage of materials was less than the standard allowed because the Company planned to produce 3,000 units of its single product during November in which the standards for one unit of the product specify six pounds of materials at $0.30 per pound but at the end the Actual production in November was 3,100 units instead of 3,000 unit which was planned.

    Therefore Materials quantity variance = (AQ - SQ) SP.

    A favorable materials quantity variance can occurred in a situation where the actual usage of materials was less than the standard allowed which is AQ < SQ.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Tower Company planned to produce 3,000 units of its single product, Titactium, during November. The standards for one unit of Titactium ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers