Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty' variable utilities costs per machine hour. Round your answer to the nearest cent. Cost Machine Hours March $3,100 15,000 April 2,700 10,000 May 2,900 12,000 June 3,600 18,000 a. $0.67 b. $10.00 c. $0.63 d. $0.11
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty' variable ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.