Ask Question
12 September, 08:58

Sanchez Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a $10,475 unfavorable direct labor rate variance and a $4,190 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?

+4
Answers (1)
  1. 12 September, 11:51
    0
    the actual total direct labor cost for the current period is $425,285

    Explanation:

    Reconciling Standard Cost to Actual Cost

    Standard Cost $419,000

    Add Unfavorable direct labor rate variance $10,475

    Less Favorable direct labor efficiency variance ($4,190)

    Actual Cost $425,285
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sanchez Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers