Sanchez Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a $10,475 unfavorable direct labor rate variance and a $4,190 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sanchez Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.