Which of the following activities illustrates a risk response strategy designed to research a threat or an opportunity?

a. establish triggers and update them frequently

b. establish time or cost contingencies

c. construct a prototype to learn more about a candidate solution

d. identify a risk owner to each high priority risk

+5
Answers (1)
  1. 31 January, 02:15
    0
    c. construct a prototype to learn more about a candidate solution.

    Explanation:

    In Business management, constructing a prototype to learn more about a candidate solution is a risk response strategy designed to research a threat or an opportunity.

    Also, training a member of a team to cover for a potentially unavailable key resource is a risk response strategy designed to mitigate a threat.

    There are mainly four (4) risk response strategies;

    - Avoidance.

    - Transferring.

    - Mitigation.

    - Acceptance.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following activities illustrates a risk response strategy designed to research a threat or an opportunity? a. establish ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.