A bucket that weighs 4 lb and a rope of negligible weight are used to draw water from a well that is 90 ft deep. The bucket is filled with 40 lb of water and is pulled up at a rate of 1.5 ft/s, but water leaks out of a hole in the bucket at a rate of 0.15 lb/s. Find the work done in pulling the bucket to the top of the well.

+3
Answers (1)
  1. 23 July, 13:06
    0
    The work on the bucket is a function of height--->h

    dwork = F (h) * dh

    dwork = weight (h) * dh

    weight (t) = 44 - 0.2t

    but t = h/v

    weight (h) = 44 - 0.2 (h/v) - - - >[44 - 8] = 36 lbs at top

    work = ∫ weight (h) * dh

    work = ∫[44 - 0.2 (h/v) ] dh ft

    work = ∫[44 - 0.1h] dh ft

    work = 44h - 0.1*0.5*h^2 ft

    work = 44*80 - (0.1*0.5*80^2) = 3200 ft-lbs
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A bucket that weighs 4 lb and a rope of negligible weight are used to draw water from a well that is 90 ft deep. The bucket is filled with ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.