Dan can tile a floor in 3 hours. his assistant could tile the same floor in 8 hours. if they work together, how long will it take to tile the floor?

+3
Answers (1)
  1. 18 September, 18:02
    0
    There is a formula for this:

    Total Time = (worker1 * worker2) / (worker1 + worker2)

    (3 * 8) / (3 + 8)

    24 / 11 =

    2.1818181818 hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Dan can tile a floor in 3 hours. his assistant could tile the same floor in 8 hours. if they work together, how long will it take to tile ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.