You have been assigned to a new project to build a boat manufacturing production line. You have built several similar production lines in the past and the technology you will use is very familiar to you. The customer is very clear about his requirements and goals. Which project management approach would you use for this project? Group of answer choices a) Agile b) Waterfall c) Matrix d) Industrial.

+2
Answers (1)
  1. 30 October, 23:24
    0
    Waterfall

    Waterfall is the answer
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “You have been assigned to a new project to build a boat manufacturing production line. You have built several similar production lines in ...” in 📙 Social Studies if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.